Construction Timeline: |
|||
|
Sprinkler system to be installed - Complete |
|||
| Sod to be laid and Goal Posts installed - Complete | |||
| Electrical connections to be installed - Complete | |||
| Foundation for the Grandstand to be poured - Complete | |||
| Press Box to be installed - Complete | |||
| Grandstand to be installed - Complete | |||
| Scoreboard to be installed - Complete | |||
|
|
|||
| July 17, 2005 - A view of the South End Zone from the stands. | |||
|
|
|||
| July 17, 2005 - A view of the North End Zone from the stands. | |||
|
|
|||
| July 17, 2005 - The Scoreboard has arrived. | |||
|
|
|||
| July 17, 2005 - The Grandstands and Press Box are near completion. | |||
|
|
|||
| July 17, 2005 - The Press Box is installed. | |||
|
|
|||
| July 15, 2005 - Grandstand construction is underway. | |||
|
|
|||
| July 1, 2005 - The Goal Posts go up. | |||
|
|
|||
| June 29, 2005 - The sod is being installed... | |||
|
|
|||
| and the field is starting to take shape. | |||
|
|
|||
| June 29, 2005 - The Lights are working...most of them anyway. | |||
|
|
|||
| June 26, 2005 - The Goal Post bases have been installed. | |||
![]() |
|||
| June 15, 2005 - Installation of the sprinkler system is underway. | |||
![]() |
|||
| June 15, 2005 - The foundation for the Grandstand starts to take shape. | |||
![]() |
|||
| June 15, 2005 - The Goal Posts have arrived. | |||
|
|
|||
|
May 30, 2005 - The preliminary field layout is complete. |
|||